Question #: 190
Topic #: 7
A company manufactures banana hooks for retail sale. The bill of materials for this item and the parts inventory for each material required are as follows:

An incoming order calls for deliver," of 2,000 banana hooks in 2 weeks. The company has
200 finished banana hooks in current inventory. If no safety stocks are required for inventory, what are the company's net requirements for swag hooks and screws needed to fill this order?

Suggested Answer: B Vote an answer

The company needs 1,800 banana hooks 2,000 - 200) and therefore 1,800 swag hooks 1 1,800) and 3,600 wood screws 2 1,800). Given that 300 swag hooks and 400 wood screws are on hand, the company must obtain 1,500 swag hooks 1,800 - 300) and 3,200 wood screws 3,600 400).

by Devin at Nov 01, 2025, 05:54 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10