Which of the following statements regarding the necessary resources to achieve the internal audit plan is true?
Suggested Answer: C Vote an answer
According to the Standards, internal audit activities can be provided through in-house resources, outsourcing, or a co-sourcing model. Therefore, it is possible for all resources to come from outside the organization, but ultimate responsibility and accountability remain with the CAE, management, and the board.
Option A is incorrect because oversight cannot be outsourced. Option B is incorrect-coordination with other assurance providers typically increases efficiency. Option D misstates requirements; co-sourcing is an option, not a mandatory practice.
Reference:
IIA Standards - Standard 2070: External Service Provider and Organizational Responsibility for Internal Auditing.
Option A is incorrect because oversight cannot be outsourced. Option B is incorrect-coordination with other assurance providers typically increases efficiency. Option D misstates requirements; co-sourcing is an option, not a mandatory practice.
Reference:
IIA Standards - Standard 2070: External Service Provider and Organizational Responsibility for Internal Auditing.
by Miles at Nov 18, 2025, 01:56 AM