Exam IIA-CRMA Topic 5 Question 34 Discussion

Actual exam question for IIA's IIA-CRMA exam
Question #: 34
Topic #: 5
Which of the following are components of the ISO 31000 risk management process?
1. Setting the context.
2. Risk treatment.
3. Risk avoidance.
4. Communication.

Suggested Answer: A Vote an answer

by BLOOD1442 at Dec 21, 2025, 03:25 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
BLOOD1442
2025-12-21 15:25:29
Selected Answer: B
1. Setting the context (Correct): This is the foundational step where you define the scope and criteria.

2. Risk treatment (Correct): This is the stage where you decide how to respond to the risks.

4. Communication (Correct): This is the continuous "wrapper" activity that ensures stakeholders are involved.
upvoted 1 times
...
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0