Which component of ITIL involves the creation of an RFC ticket and obtaining official approvals for it?
Suggested Answer: D Vote an answer
Explanation
The change management process involves the creation of the official Request for Change (RFC) ticket, which is used to document the change, obtain the required approvals from management and stakeholders, and track the change to completion. Release management is a subcomponent of change management, where the actual code or configuration change is put into place. Deployment management is similar to release management, but it's where changes are actually implemented on systems. Problem management is focused on the identification and mitigation of known problems and deficiencies before they are able to occur.
The change management process involves the creation of the official Request for Change (RFC) ticket, which is used to document the change, obtain the required approvals from management and stakeholders, and track the change to completion. Release management is a subcomponent of change management, where the actual code or configuration change is put into place. Deployment management is similar to release management, but it's where changes are actually implemented on systems. Problem management is focused on the identification and mitigation of known problems and deficiencies before they are able to occur.
by Deborah at Nov 05, 2024, 10:21 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).