Exam CTAL-TA_V4.0 Topic 1 Question 6 Discussion

Actual exam question for ISQI's CTAL-TA_V4.0 exam
Question #: 6
Topic #: 1
You are working on an Agile project to develop a web-based online dating service that will allow members of the service to enter their profile, meet people who would be a good match for them, arrange social events with those people and to block people with whom they do not want contact.
The features for member profile entry have been delivered and tested. The current iteration will deliver profile matching. The regression tests for profile entry will be the acceptance criteria for its user stories. These tests have not been automated yet so you have decided to perform regression testing on the basis of a checklist.
Which checklist would be BEST in these circumstances?

Suggested Answer: A Vote an answer

The correct answer is A . CTAL-TA v4.0 describes checklist-based testing as an experience-based technique in which checklist items guide the tester and help avoid missing important checks. It distinguishes checklist use from fully scripted testing, but the checklist must still be concrete enough to support the objective of the test session.
Here, the goal is regression testing for profile entry. The scenario says the regression tests for profile entry will be the acceptance criteria for its user stories , but those tests have not been automated yet. Since the team needs to manually perform regression testing now, the best checklist is a read-do checklist built from the acceptance tests of the user stories. A read-do checklist is appropriate when the tester should read each item and perform it as an action. That fits manual regression execution: run this acceptance test, check the result, then proceed to the next item.
Option B is weaker because acceptance criteria are statements of expected behavior, not necessarily executable test actions. Option C is less suitable because a do-confirm checklist is used when tasks are performed from memory or normal workflow and then checked afterward; regression testing needs active, item-by-item execution. Option D combines both weaknesses: acceptance criteria instead of acceptance tests, and do-confirm instead of read-do. Reference: CTAL-TA v4.0, Section 3.4.2 Checklists Supporting Experience-Based Test Techniques .

by Julie at Aug 12, 2026, 07:08 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10