Exam ITIL-4-Foundation Topic 5 Question 318 Discussion

Actual exam question for ITIL's ITIL-4-Foundation exam
Question #: 318
Topic #: 5
What can a change schedule be used for?

Suggested Answer: B Vote an answer

The change schedule is used to help plan changes, assist in communication, avoid conflicts, and assign resources. It can also be used after changes have been deployed to provide information needed for incident management, problem management, and improvement planning
https://www.bmc.com/blogs/itil-change-enablement/#:~:text=The%20change%20schedule%20is%20used,problem%20management%2C%20and%20improvement%20planning.

by Althea at Aug 25, 2025, 10:55 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10