Exam ITIL-4-Foundation Topic 7 Question 65 Discussion

Actual exam question for ITIL's ITIL-4-Foundation exam
Question #: 65
Topic #: 7
Which value chain activity is concerned with the availability of service components?

Suggested Answer: D Vote an answer

The Obtain/Build activity is responsible for ensuring that all service components are available when and where needed, and that they meet the agreed specifications.
https://www.beyond20.com/blog/what-is-the-itil-4-service-value-chain/#:~:text=The%20Obtain%2FBuild%
20activity%20is,they%20meet%20the%20agreed%20specifications.

by Zebulon at Dec 29, 2025, 10:57 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10