Which of the following best describes the architect's role in cost estimating during schematic design?
Suggested Answer: B Vote an answer
During schematic design, the architect provides a preliminary opinion of probable construction cost (OPCC) based on conceptual design. This estimate is less detailed but important for budgeting and feasibility analysis.
It helps the owner make informed decisions about project scope and design direction early in the process.
Detailed quantity takeoffs and vendor pricing occur later in the design development or construction documents phases. Verifying bids and approving final budgets are responsibilities tied to later stages. The ARE 5.0 PjM exam highlights early-stage cost estimating as a critical tool for scope control and project feasibility.
It helps the owner make informed decisions about project scope and design direction early in the process.
Detailed quantity takeoffs and vendor pricing occur later in the design development or construction documents phases. Verifying bids and approving final budgets are responsibilities tied to later stages. The ARE 5.0 PjM exam highlights early-stage cost estimating as a critical tool for scope control and project feasibility.
by Baldwin at Jul 26, 2026, 04:43 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).