Exam ISO-9001-Lead-Auditor Topic 2 Question 179 Discussion

Actual exam question for PECB's ISO-9001-Lead-Auditor exam
Question #: 179
Topic #: 2
You, as auditor, are in dialogue with the quality lead and managing director of a small business that supplies specialist laboratory equipment and furniture.
You: "I'd like to look at how you manage change in the organisation. What changes have you made as a business, say, over the last 12 months?" Auditee: "We have made some strategic changes, the main one being that we no longer manufacture our own products in house." You: "That sounds like quite a significant change. What has been the impact of that?" Auditee: "We now mainly sell other manufacturers' products, under their brand names, and have outsourced manufacture of our own brand products to one of our suppliers. Unfortunately, we had to make six members of our staff redundant. This represents about 20% of our workforce, so this has been quite a challenging time." You: "I'm sure. What were the reasons for making the change?" Auditee: "Our manufacturing section was a small operation, and we struggled to cope with fluctuations in demand. During busy periods, we found it hard to meet lead times, and in quiet periods we had staff with little to do. This was having an impact on customer satisfaction and meant we had to charge premium prices that made our product uncompetitive." You: "How did you go about the change?" In relation to the auditor's question about how the change was managed, the auditee mentions the steps listed below. Match the ISO 9001 clauses to the steps.
To complete the table, click on the blank section you want to complete so it is highlighted in red and then click on the ISO 9001 clauses listed below. Alternatively, drag and drop each clause to show which step the requirement applies to.

Suggested Answer:


Explanation:

Here is the correct matching of ISO 9001:2015 clauses to the steps mentioned in the change management process:
* We identified risks and opportunities and fed these into our risk management processes.
* Clause 6.1 (Actions to address risks and opportunities)
* We found a suitable supplier.
* Clause 8.4 (Control of externally provided processes, products, and services)
* We monitored customer feedback and noticed an increase in negative feedback about lead times.
* Clause 9.1.2 (Customer satisfaction)
* We put together a plan for implementation.
* Clause 6.2.2 (Planning to achieve quality objectives)
* We monitored the performance of the new supplier.
* Clause 8.4.2 (Type and extent of control of external providers)
* We noticed that productivity targets were being missed.
* Clause 9.1.1 (Monitoring, measurement, analysis, and evaluation)
* We communicated the plan internally.
* Clause 7.4 (Communication)
* We looked at the data at the management review and decided we needed to do something different.
* Clause 9.3.2 (Management review inputs)
* We reorganised the staffing and implemented redundancies.
* Clause 7.1.2 (People)
* We set an objective to effectively implement the transition and outsource manufacturing.
* Clause 6.2.1 (Quality objectives and planning to achieve them)
This aligns the steps of the change process with relevant ISO 9001:2015 clauses related to risk, planning, communication, and monitoring.

by Celeste at May 06, 2026, 12:41 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10