Question #: 108
Topic #: 3
What is the responsibility of the audit committee during an internal audit?

Suggested Answer: C Vote an answer

Comprehensive and Detailed In-Depth Explanation:
According to ISO 19011:2018, Clause 5.2 (Audit Program Management):
* The audit committee is responsible for establishing the internal audit program.
* The audit schedule (A) is determined within the program, but it is not the main role of the committee.
Thus, C is the correct answer.
Reference:
ISO 19011:2018, Clause 5.2 (Audit Program Management)

by Dolores at Sep 10, 2025, 05:11 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10