Exam ISO-9001-Lead-Auditor Topic 3 Question 108 Discussion
Actual exam question for PECB's ISO-9001-Lead-Auditor exam
Question #: 108
Topic #: 3
Question #: 108
Topic #: 3
What is the responsibility of the audit committee during an internal audit?
Suggested Answer: C Vote an answer
Comprehensive and Detailed In-Depth Explanation:
According to ISO 19011:2018, Clause 5.2 (Audit Program Management):
* The audit committee is responsible for establishing the internal audit program.
* The audit schedule (A) is determined within the program, but it is not the main role of the committee.
Thus, C is the correct answer.
Reference:
ISO 19011:2018, Clause 5.2 (Audit Program Management)
According to ISO 19011:2018, Clause 5.2 (Audit Program Management):
* The audit committee is responsible for establishing the internal audit program.
* The audit schedule (A) is determined within the program, but it is not the main role of the committee.
Thus, C is the correct answer.
Reference:
ISO 19011:2018, Clause 5.2 (Audit Program Management)
by Dolores at Sep 10, 2025, 05:11 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).