Implement plan on a test basis - this comes under which section of PDCA
Suggested Answer: B Vote an answer
Explanation
The PDCA cycle is a four-step method for managing and improving processes. The steps are Plan, Do, Check, and Act. In the Plan phase, the objectives and scope of the process are defined, and the resources and activities are planned. In the Do phase, the process is implemented on a test basis, and the results are recorded and analyzed1. References: ISO/IEC 27001:2022 Lead Auditor (Information Security Management Systems) | CQI
| IRCA
The PDCA cycle is a four-step method for managing and improving processes. The steps are Plan, Do, Check, and Act. In the Plan phase, the objectives and scope of the process are defined, and the resources and activities are planned. In the Do phase, the process is implemented on a test basis, and the results are recorded and analyzed1. References: ISO/IEC 27001:2022 Lead Auditor (Information Security Management Systems) | CQI
| IRCA
by Nick at May 28, 2025, 01:50 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).