Exam CPMAI_v7 Topic 4 Question 33 Discussion
Actual exam question for PMI's CPMAI_v7 exam
Question #: 33
Topic #: 4
Question #: 33
Topic #: 4
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.
What's wrong with this timeframe?
What's wrong with this timeframe?
Suggested Answer: C Vote an answer
CPMAI's Phase III: Data Preparation is a distinct phase that encompasses data cleansing, augmentation, labeling, and pipeline construction. Because data engineering often accounts for the majority of AI project effort, omitting this phase from initial estimates leads to significant timeline underestimation. Project timelines must explicitly include Phase III activities to be realistic .
=========
=========
by Daniel at Jul 27, 2026, 04:37 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).