Exam PMI-ACP Topic 3 Question 174 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 174
Topic #: 3
After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

Suggested Answer: B Vote an answer

by Colin at Oct 28, 2025, 12:12 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.