In a government healthcare AI project, the objective is to reduce patient wait times by optimizing staff schedules. After 6 months, the cost is US$500,000 with a completion rate of 60%. The project manager needs to determine the return on investment (ROI) to justify the current expenditure. What is an effective method to achieve this objective?
Suggested Answer: D Vote an answer