Exam PMI-RMP Topic 2 Question 233 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 233
Topic #: 2
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?

Suggested Answer: B Vote an answer

Explanation
Centralizing the risk management function enables the organization to have a consistent approach to reporting risks and their impacts. This allows for better monitoring of the impact against the overall project risk exposure, which helps in making informed decisions and allocating resources effectively.

by Salome at Oct 15, 2026, 08:04 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10