After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
How could the risk manager have avoided the board's response?
Suggested Answer: A Vote an answer
According to the PMBOK Guide, risk prioritization is the process of assigning a level of importance to each identified risk based on its probability and impact, as well as other factors such as urgency, stakeholder tolerance, and project objectives. Risk prioritization helps the project team to focus on the most significant risks and allocate resources accordingly. One of the tools and techniques for risk prioritization is stakeholder engagement, which involves involving the key stakeholders in the risk analysis and decision making process. Stakeholder engagement helps to ensure that the risk prioritization reflects the expectations and preferences of the stakeholders, and that they are aware of and agree with the results. By engaging the key stakeholders during the prioritization process, the risk manager could have avoided the board's request to sort the risks differently, as the board would have been part of the process and would have accepted the outcome. Reference: = PMBOK Guide, 6th edition, pages 406-407; The Standard for Risk Management in Portfolios, Programs, and Projects, page 67.
by Betty at Feb 06, 2026, 05:35 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).