Exam PMI-RMP Topic 7 Question 93 Discussion
Actual exam question for PMI's PMI-RMP exam
Question #: 93
Topic #: 7
Question #: 93
Topic #: 7
At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________
Suggested Answer: C Vote an answer
The primary outputs from identify risks are initial entries into the risk register. It ultimately contains outcomes of other risk management processes as they are conducted. As an output of identify risks, the risk register should contain a list of identified risks, a list of potential responses, root causes that gave rise to the identified risks, and a structure for describing risks. [Planning] PMIĀ®, PMBOKĀ® Guide, 2013, 327
by Ives at Aug 09, 2026, 12:02 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).