Question #: 319
Topic #: 5
Yolanda is the project manager for her organization. She is creating a performance report for her sponsor.
Typically, the performance report includes all of the following factors except for which one?

Suggested Answer: B Vote an answer

Explanation/Reference:
Explanation:
Quality control activities are not included in the performance report, but are documented in the quality management plan. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are used to report some key information as follows: Current status Scheduled activities Significant accomplishment for the period Forecasts Issues Incorrect Answers:
A: Current status of risk and issues can be included in the performance report.
C: Analysis of past performance can be included in the performance report to make the report more elaborate.
D: Work to be completed next can be included in the performance report.

by Kyle at Jan 25, 2025, 01:42 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10