Exam PMP Topic 1 Question 1025 Discussion
Actual exam question for PMI's PMP exam
Question #: 1025
Topic #: 1
Question #: 1025
Topic #: 1
Accurate and unbiased data are essential for perform qualitative risk analysis. Which one of the following should you use to examine the extent of understanding of project risk?
Suggested Answer: A Vote an answer
Section: Mix Questions
Explanation:
Perform qualitative risk analysis requires accurate and unbiased data. The use of low-quality data may result in a qualitative risk analysis that is of little use to the project manager regarding understanding of the risk, data available about the risk, data quality, and data reliability and integrity.
Explanation:
Perform qualitative risk analysis requires accurate and unbiased data. The use of low-quality data may result in a qualitative risk analysis that is of little use to the project manager regarding understanding of the risk, data available about the risk, data quality, and data reliability and integrity.
by Randolph at Apr 01, 2026, 12:49 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).