Exam PMP Topic 1 Question 136 Discussion

Actual exam question for PMI's PMP exam
Question #: 136
Topic #: 1
A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?

Suggested Answer: B Vote an answer

It's important for the project manager to meet with the local community in person to share the good news and address any concerns they may have. This will help to build trust and strong relationship with the community. Additionally, some people in rural areas may not have regular access to email or internet, so it's important to consider other means of communication. And holding a meeting will be the best option to reach all stakeholders.

by Lynn at Jun 13, 2026, 03:07 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10