Exam PMP Topic 1 Question 142 Discussion

Actual exam question for PMI's PMP exam
Question #: 142
Topic #: 1
Your customer ask for a small change in the project, which was not budgetted in the project. It is a small effort as compared to the total project and you need the goodwill for a multimillion dollar on the pipeline. You will

Suggested Answer: D Vote an answer

by Valentine at Jul 23, 2026, 03:55 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10