If you want to calculate the ETC based on your expectations that similar variances to those noted to date will not occur, you should use which of the following formulas?

Suggested Answer: A Vote an answer

Section: Mix Questions
Explanation:
This formula assumes that the estimate to complete is based on the same cost efficiency level.