Exam PMP Topic 1 Question 159 Discussion
Actual exam question for PMI's PMP exam
Question #: 159
Topic #: 1
Question #: 159
Topic #: 1
The release of a mobile application is near. However, the team is experiencing a major regulatory approval delay for the application's graphics. This delay will impact the launch of the mobile app.
What should the project manager do?
What should the project manager do?
Suggested Answer: C Vote an answer
The correct answer is C because the scenario requires disciplined risk management rather than an immediate, informal, or purely administrative reaction. The selected response - C. Update the risk register with the team and escalate to the project sponsor and steering committee. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to identify the event or uncertainty, assess probability and impact, document ownership, and select a response that protects project objectives. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK Guide Eighth Edition topics: business environment, risk management, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
by e.shaabanpm at Jul 24, 2026, 01:08 AM
0
0
0
10
Comments
e.shaabanpm
2026-07-24 01:08:02When an external risk event (regulatory approval delay) materializes into an issue impacting project completion, the PM must log/update the risk register and escalate to leadership governance bodies.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.