All the following statements regarding critical chain method are true EXCEPT______________

Suggested Answer: B Vote an answer

Section: Mix Questions
Explanation:
When using critical chain techniques, the initial project schedule is developed using duration estimates with required dependencies and defined constraints as inputs.