Question #: 2041
Topic #: 1
The project manager of a pipeline project hires a construction contractor using a cost plus fixed fee (CPFF) contract, the contractor provides the project manager with an estimate of US$50,000, and a fixed-fee amount of US$5,000. When the pipeline is completed, the construction cost is US$60,000.
What amount should the contractor be paid?

Suggested Answer: B Vote an answer