Exam PMP Topic 1 Question 377 Discussion
Actual exam question for PMI's PMP exam
Question #: 377
Topic #: 1
Question #: 377
Topic #: 1
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
What should the project manager have done to avoid this situation?
Suggested Answer: C Vote an answer
The project manager should have ensured that the project repository is up to date and contains all the relevant information and documentation related to the project deliverables, such as user stories, acceptance criteria, test cases, design specifications, etc. This way, the remaining team members can access the information they need to continue working on the deliverable, even if a senior team member leaves the organization. This practice is consistent with the agile principle of maintaining a single source of truth and ensuring transparency and collaboration among the team members12. References: 1: PMBOK Guide, 6th Edition, Chapter 4: Project Integration Management 2: Agile Practice Guide, Chapter 3: Life Cycle Selection
by kyzyrhan38 at Apr 10, 2026, 04:23 AM
0
0
0
10
Comments
kyzyrhan38
2026-04-10 04:24:11Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).