Exam PMP Topic 1 Question 645 Discussion

Actual exam question for PMI's PMP exam
Question #: 645
Topic #: 1
During project execution, an operator identifies a requirement that was not addressed in the project management plan. The team is conflicted about whether or not this requirement should be added as a change request.
What should the project manager have done to avoid this situation?

Suggested Answer: B Vote an answer

Section: Executing