During project execution, an operator identifies a requirement that was not addressed in the project management plan. The team is conflicted about whether or not this requirement should be added as a change request.
What should the project manager have done to avoid this situation?
What should the project manager have done to avoid this situation?
Suggested Answer: B Vote an answer