Exam PMP Topic 1 Question 697 Discussion

Actual exam question for PMI's PMP exam
Question #: 697
Topic #: 1
If you apply the configuration management system along with change control processes project wide, you will achieve all but one of the which following objectives?

Suggested Answer: C Vote an answer

Explanation/Reference:
Explanation:
Configuration management is an integral part of the perform integrated change control process. It is necessary because projects by their nature involve changes. The integrity of baselines must be maintained by releasing only approved changes for incorporation into the project's products or services and by maintaining their related configuration and planning documentation.

by Albert at Sep 16, 2025, 08:02 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10