A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
Suggested Answer: D Vote an answer
During execution, any addition to scope must go through the formal change control process. The project manager should initiate a change request for proper evaluation and approval. This ensures that scope, budget, and schedule impacts are assessed before proceeding.
According to the PMBOK Guide - Seventh Edition, any changes to the baseline during execution must follow the change control procedures defined in the governance structure.
Option A risks scope creep.
Option B is helpful but not sufficient as a next step.
Option C closes the door without considering the critical nature of the request.
References:
PMBOK Guide - Seventh Edition, Delivery and Planning Performance Domains PMI Change Control and Governance Guidelines
According to the PMBOK Guide - Seventh Edition, any changes to the baseline during execution must follow the change control procedures defined in the governance structure.
Option A risks scope creep.
Option B is helpful but not sufficient as a next step.
Option C closes the door without considering the critical nature of the request.
References:
PMBOK Guide - Seventh Edition, Delivery and Planning Performance Domains PMI Change Control and Governance Guidelines
by Guy at Nov 11, 2025, 03:25 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).