A pipe manufacturer for a water pipeline project conducts sample testing without the presence of the client's quality assurance manager. The quality management plan clearly states that the client and quality assurance manager must be present during such tests. The manufacturer, however, insists that such approvals are unnecessary due to its longstanding business relationship with the client.
What should the project manager do?
What should the project manager do?
Suggested Answer: B Vote an answer
Section: Monitoring and Controlling