Exam PMP Topic 2 Question 1083 Discussion

Actual exam question for PMI's PMP exam
Question #: 1083
Topic #: 2
A project manager is developing the change management plan with the team. A team member points out that the customer will not accept any changes, despite the fact that contract terms allow for them. The team member believes that developing a change management plan is a waste of time.
What should the project manager do?

Suggested Answer: B Vote an answer

Section: Planning