Exam PMP Topic 2 Question 1150 Discussion

Actual exam question for PMI's PMP exam
Question #: 1150
Topic #: 2
When writing payment terms in your fixed-price subcontracts it is especially important to______________

Suggested Answer: C Vote an answer

Explanation/Reference:
Explanation:
A buyer under a fixed-price contract should pay a seller for work delivered rather than time expended.
Linking payment with progress ensures that the seller will focus on results and not on effort expended.

by Maximilian at Oct 02, 2025, 08:13 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10