Exam PMP Topic 2 Question 1303 Discussion

Actual exam question for PMI's PMP exam
Question #: 1303
Topic #: 2
The following is a network diagram for a project.

The free float for Activity E is how many days?

Suggested Answer: D Vote an answer

by Octavia at May 17, 2026, 03:23 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10