A project team is tasked with implementing a new technology system for the end users. The project team currently lacks information on what the system is used for and how the end users would use it.
What should the project manager do?
What should the project manager do?
Suggested Answer: D Vote an answer
The correct answer is D because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response - D. Ask the sponsor to define the project objectives and goals in the project documents. - directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK Guide Eighth Edition topics:
business environment, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
business environment, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.
by e.shaabanpm at Jul 23, 2026, 11:18 PM
0
0
0
10
Comments
e.shaabanpm
2026-07-23 23:18:36When fundamental project objectives and usage context are missing, the project manager must engage the executive sponsor to define business goals and project objectives within foundational charter documents.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.