A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week.
What should the project manager do next?
What should the project manager do next?
Suggested Answer: A Vote an answer
In this scenario, the project manager is facing a delay from a supplier that could impact a key project milestone. The first step should be to communicate with the vendor to explore possible solutions. This could include asking if the vendor can produce a minimally sufficient quantity of the key component in time to meet the project's immediate needs12. This approach allows the project to stay on track while also addressing the supplier's production challenges. It's important to note that this is a short-term solution and the project manager will need to continue to work with the supplier to resolve the longer-term production issues. References: Project Procurement Management - A Quick Guide, 7 factors to consider when working with project suppliers
by Amelia at Dec 31, 2025, 03:39 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).