Exam PMP Topic 2 Question 163 Discussion
Actual exam question for PMI's PMP exam
Question #: 163
Topic #: 2
Question #: 163
Topic #: 2
Project managers for international projects should recognize key issues in cross-cultural settings and place special emphasis on______________
Suggested Answer: B Vote an answer
Section: Mix Questions
Explanation:
An effective way to manage cultural diversity on projects is for the project manager to get to know the team members and to use good communication planning. It is necessary to consider time zones and language barriers as well as cultural differences and to include a glossary of common terminology in the communications management plan.
Explanation:
An effective way to manage cultural diversity on projects is for the project manager to get to know the team members and to use good communication planning. It is necessary to consider time zones and language barriers as well as cultural differences and to include a glossary of common terminology in the communications management plan.
by Owen at Jul 17, 2026, 11:24 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).