Exam PMP Topic 2 Question 1820 Discussion

Actual exam question for PMI's PMP exam
Question #: 1820
Topic #: 2
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?

Suggested Answer: B Vote an answer

When a project encounters a quality issue, such as an unacceptably high defect rate in early prototypes, the first step for the project manager should be to assemble a problem-solving team. This team should consist of quality assurance subject matter experts (SMEs) who have experience in this type of analysis. The team will then perform a cause-and-effect analysis to identify the root cause of the quality problem. Once the root cause is identified, the team can develop and implement a solution to address the issue, thereby improving the quality of the project deliverables. References: PMI's Project Management Professional (PMP)Examination Content Outline1, PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline2.

by Webb at Feb 26, 2026, 08:39 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10