Exam PMP Topic 2 Question 238 Discussion

Actual exam question for PMI's PMP exam
Question #: 238
Topic #: 2
The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?

Suggested Answer: B Vote an answer