Exam PMP Topic 2 Question 28 Discussion

Actual exam question for PMI's PMP exam
Question #: 28
Topic #: 2
Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?

Suggested Answer: D Vote an answer