Exam PMP Topic 2 Question 363 Discussion

Actual exam question for PMI's PMP exam
Question #: 363
Topic #: 2
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?

Suggested Answer: B Vote an answer