To account for uncertainty in a schedule, reserve analysis may be used. All the following are examples of contingency reserves EXCEPT ______________
Suggested Answer: D Vote an answer
Section: Mix Questions
Explanation:
Duration estimates may include contingency reserves, and contingency should be identified clearly in schedule documentation. They are built into the overall project schedule to account for uncertainty. They also may be developed using quantitative analysis methods. When more information is known about the project, the contingency reserve may be used, reduced, or eliminated.
Explanation:
Duration estimates may include contingency reserves, and contingency should be identified clearly in schedule documentation. They are built into the overall project schedule to account for uncertainty. They also may be developed using quantitative analysis methods. When more information is known about the project, the contingency reserve may be used, reduced, or eliminated.
by Teresa at Jul 27, 2025, 12:44 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).