Exam PMP Topic 2 Question 608 Discussion
Actual exam question for PMI's PMP exam
Question #: 608
Topic #: 2
Question #: 608
Topic #: 2
A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
What should the project manager do next?
Suggested Answer: A Vote an answer
When a project milestone is missed due to a team member not completing their tasks on time, it is important for the project manager to address the issue directly with the individual involved. A one-on-one meeting allows for a private discussion where the project manager can understand the reasons behind the delay, provide feedback, and work with the team member to develop a plan to prevent future issues. This approach is aligned with the best practices for project human resource management, which emphasize the importance of clear communication and problem-solving within the project team.
: = The PMP Examination Content Outline1 and the PMBOK Guide2 highlight the importance of project communication and human resource management. The Professional in Business Analysis Reference Materials also suggest direct engagement with team members to address project challenges3.
: = The PMP Examination Content Outline1 and the PMBOK Guide2 highlight the importance of project communication and human resource management. The Professional in Business Analysis Reference Materials also suggest direct engagement with team members to address project challenges3.
by Stanley at Jun 03, 2026, 12:20 PM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).