Question #: 62
Topic #: 2
An Activity has an Optimistic estimate of 10 days, pessimistic estimate of 16 days, most
likely estimate of 13 days. If your company has a quality requirement of 6 sigma, what is the duration within which this task must be completed?

Suggested Answer: D Vote an answer