Question #: 692
Topic #: 2
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again What should the project lead do next?

Suggested Answer: D Vote an answer