Exam PMP Topic 2 Question 747 Discussion
Actual exam question for PMI's PMP exam
Question #: 747
Topic #: 2
Question #: 747
Topic #: 2
The project manager has calculated the schedule performance index (SPI) as 1 and cost performance index (CPI) as 1.2.
What is the status of the project?
What is the status of the project?
Suggested Answer: D Vote an answer