Exam PRINCE2-Foundation Topic 1 Question 157 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 157
Topic #: 1
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?

Suggested Answer: D Vote an answer

Similar to question 411, the answer remains consistent for monitoring the progress of a stage. The combination of Highlight Reports and Checkpoint Reports provides the project manager with both high-level and detailed insights into the stage's progress. Highlight Reports summarize stage status for the Project Board, while Checkpoint Reports offer detailed progress updates from the team level.References:
(PRINCE2 7 Foundation Handbook, AXELOS)

by Myrna at Aug 23, 2026, 06:42 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10