Exam PRINCE2-Foundation Topic 1 Question 157 Discussion
Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 157
Topic #: 1
Question #: 157
Topic #: 1
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?
Which combination of management products should the project manager review?
Suggested Answer: D Vote an answer
Similar to question 411, the answer remains consistent for monitoring the progress of a stage. The combination of Highlight Reports and Checkpoint Reports provides the project manager with both high-level and detailed insights into the stage's progress. Highlight Reports summarize stage status for the Project Board, while Checkpoint Reports offer detailed progress updates from the team level.References:
(PRINCE2 7 Foundation Handbook, AXELOS)
(PRINCE2 7 Foundation Handbook, AXELOS)
by Myrna at Aug 23, 2026, 06:42 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).