Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 24
Topic #: 1
Question #: 24
Topic #: 1
Which level of management sets the project level tolerances?
Suggested Answer: D Vote an answer
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_exception
Reference http://prince2.wiki/Manage_by_exception