Exam C_STC_2405 Topic 2 Question 57 Discussion

Actual exam question for SAP's C_STC_2405 exam
Question #: 57
Topic #: 2
A project-specific deliverable is not part of the SAP Activate roadmap. How can you manage all tasks that are related to that deliverable?

Suggested Answer: B Vote an answer

When a project-specific deliverable is not included in the standard SAP Activate roadmap, you can manage it by creating a custom deliverable in SAP Cloud ALM. This allows for tracking tasks and milestones specific to that deliverable within the project.
Reference:
SAP Cloud ALM Custom Deliverable Guide
SAP Help Portal on SAP Activate Roadmap Customization

by Cecilia at Oct 15, 2026, 08:52 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10