Exam C_TS422_2022 Topic 8 Question 31 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 31
Topic #: 8
Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Suggested Answer: B Vote an answer