Question #: 50
Topic #: 1
Question #: 50
Topic #: 1
Which of the following are tasks during the development of VM proposals? (Choose 3 answers)
Suggested Answer: A,B,D Vote an answer
The Development Phase of the Value Methodology (VM) Job Plan involves refining selected ideas into actionable proposals, as taught in the VMF 1 course (Core Competency #3: Value Methodology Job Plan).
According to SAVE International's Value Methodology Standard, "during the Development Phase, the VM team develops proposals by addressing technical feasibility, assessing time and schedule impacts, determining costs, identifying risks, and providing implementation plans." These tasks ensure that proposals are practical, cost-effective, and ready for presentation to stakeholders.
* A. Address technical feasibility: Correct, as the team must ensure the proposal can be implemented technically (e.g., does the design work?).
* B. Assess time and schedule impacts: Correct, as the team evaluates how the proposal affects the project timeline (e.g., delays or accelerations).
* D. Determine costs: Correct, as cost modeling is a key task (as noted in Question 9), providing stakeholders with financial impacts of the proposal.
* C. State the disposition of the proposal: Incorrect, as stating the disposition (e.g., accepted, rejected) occurs after the Presentation Phase, when stakeholders decide on the proposal, not during Development.
* E. Validate the proposal: Incorrect, as validation (e.g., testing or final confirmation) typically occurs during implementation or post-study, not during Development, which focuses on creating the proposal.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing tasks in the Development Phase like technical feasibility, time impacts, and cost determination.
SAVE International, VMF 1 Core Competency #3 (Value Methodology Job Plan), emphasizing Development Phase tasks (consistent with Question 9).
According to SAVE International's Value Methodology Standard, "during the Development Phase, the VM team develops proposals by addressing technical feasibility, assessing time and schedule impacts, determining costs, identifying risks, and providing implementation plans." These tasks ensure that proposals are practical, cost-effective, and ready for presentation to stakeholders.
* A. Address technical feasibility: Correct, as the team must ensure the proposal can be implemented technically (e.g., does the design work?).
* B. Assess time and schedule impacts: Correct, as the team evaluates how the proposal affects the project timeline (e.g., delays or accelerations).
* D. Determine costs: Correct, as cost modeling is a key task (as noted in Question 9), providing stakeholders with financial impacts of the proposal.
* C. State the disposition of the proposal: Incorrect, as stating the disposition (e.g., accepted, rejected) occurs after the Presentation Phase, when stakeholders decide on the proposal, not during Development.
* E. Validate the proposal: Incorrect, as validation (e.g., testing or final confirmation) typically occurs during implementation or post-study, not during Development, which focuses on creating the proposal.
:
SAVE International, "Value Methodology Standard and Body of Knowledge," available athttps://www.value- eng.org, detailing tasks in the Development Phase like technical feasibility, time impacts, and cost determination.
SAVE International, VMF 1 Core Competency #3 (Value Methodology Job Plan), emphasizing Development Phase tasks (consistent with Question 9).
by Hedda at Jun 01, 2026, 10:37 AM